Woodford FM's projects

Brixton Square

Brixton Square

Supply and install of complete mechanical package including energy centre.

The project duration was 15 months and valued at £2.1M. This comprised of the energy centre installation with 6 gas fired boilers and CHP unit, cold water boosting and the fit out of 155 flats (all BMS controlled).

We carry out PPM to the energy centre which includes the following:

  • Maintenance of the 6 gas boilers
  • Maintenance of the CHP unit
  • Inspection of the primary buffer vessels
  • Maintenance of the heating pumps
  • Inspection of plate heat exchangers
  • Maintenance of the pressurisation units and expansion vessels
  • Maintenance of the BMS/controls systems
  • Water treatment to closed systems
  • Monthly plant inspections visits
  • Customer care visits to the flats for all plumbing, heating and ventilation.

Project details

  • Value: £2.1m
  • Project Duration: 15 months
  • Client: Barratt London

Share this project